What's Coming to Old Dobbin Plantersville Road? The Crossing Is Moving Again

Dozer

November 23, 2026 · 4 min read

What's Coming to Old Dobbin Plantersville Road? The Crossing Is Moving Again

A 90-lot first section and mass-grading bids show The Crossing at Montgomery advancing, while a newer city sewer schedule stretches key infrastructure work through late 2027.

People who travel Old Dobbin Plantersville Road southwest of Montgomery may soon see the first major site work for a subdivision that has been moving through city planning for more than two years.

The Crossing at Montgomery is planned on approximately 86.48 acres between Old Dobbin Plantersville Road and Old Plantersville Road, south of State Highway 105. The developer's June presentation described an eventual 235 single-family homes in three sections, with projected home values of $480,000 to $520,000 and an anticipated overall completion in 2030. Those values are projections, not published sale prices.

The First Section Has Grown to 90 Lots

The newest preliminary plat submitted to the City of Montgomery covers 27.0758 acres and shows 90 residential lots, two reserves and four blocks. The city engineer reported that all review comments had been addressed and recommended approval. The Planning and Zoning Commission approved the preliminary plat 4-0 on October 5.

That is four more lots than the 86 shown for Section 1 in the developer's June 2026 presentation. The earlier presentation continued to show 235 homes across the full project. Public records reviewed by Dock Line do not yet show whether the additional four lots change the overall total or were shifted from later sections.

The proposed lots are generally 65 feet wide and either 120 or 130 feet deep. Plans presented to the city include a walking trail, playground, sports field and either pickleball courts or a half basketball court. The development agreement also requires at least six park or open-space areas totaling 6.8 acres, three detention basins totaling 8.5 acres with walking trails and seating, and a 20-foot tree buffer along the railroad.

Dirt Work Is Getting Closer, but It Is Not Confirmed Underway

An invitation for bids for mass grading and detention work was published in October, with bids due November 19. The work includes preparing and grading the site and constructing stormwater-detention improvements.

The bid documents said work would begin after permit approval and that the plans had not yet been released for construction. That makes the solicitation the clearest sign that major dirt work is approaching, but it is not proof that clearing or construction has begun.

A Newer Sewer Schedule Extends Through 2027

The developer's June presentation anticipated starting Section 1 construction in September 2026 and completing its lots in February 2027. A newer city schedule no longer lines up neatly with that forecast.

The City of Montgomery's November capital-project schedule shows design of The Crossing's sanitary-sewer improvements continuing through January 5, 2027, bidding from January through early March, and construction scheduled from March 27 through December 21, 2027.

That schedule covers the sanitary-sewer project rather than every part of the subdivision, so it does not establish the first homebuilding date. It does show that essential supporting infrastructure is now expected to remain under construction well beyond the earlier February 2027 lot-completion target.

City Council authorized the city engineer in August to begin designing the sewer improvements. According to the official meeting minutes, the developer elected to proceed under the existing development agreement and is responsible for the project's cost.

Trees, Drainage and Traffic Remain Part of the Discussion

Because mass grading is planned across much of the tract, the developer requested relief from the city's detailed tree-by-tree assessment requirement. City Council approved the variance 3-1 in August. The developer proposed planting two trees per lot and preserving vegetation in common areas where feasible. The variance did not remove the project's other landscaping, planting or green-space requirements.

Planning commissioners also raised concerns about traffic, access and road safety along Old Plantersville Road. City engineers said traffic studies and intergovernmental agreements were in place, while noting that later stages would return for additional review.

The PID Could Matter to Future Buyers

The city created The Crossing at Montgomery Public Improvement District in February 2025 to reimburse eligible public infrastructure costs through assessments on property inside the development.

The executed development agreement says the reimbursement arrangement is to be funded by assessments on developed lots for 30 years and specifies $2,000 per lot annually, including principal and interest. However, Dock Line did not locate a current Service and Assessment Plan confirming that figure as the final buyer charge.

Until the final assessment documents are available, the $2,000 figure should be treated as a term in the development agreement—not a final advertised cost. Future buyers should review the PID disclosure, annual assessment and payoff terms before purchasing.

What Has Not Been Announced

The developer's June presentation included a company profile for Meritage Homes, but neither Meritage nor the city has published a formal community-opening announcement that Dock Line could locate. The final homebuilder, sales opening, updated overall lot count and first construction date therefore remain unconfirmed.

For now, The Crossing at Montgomery has advanced beyond an idea: its first preliminary plat is approved, grading and detention work has been bid, and sewer design is underway. The next visible milestone will be a permit, a construction award or machinery arriving at the property.

Illustration note: The featured image is an AI-generated editorial concept based on public planning documents. It is not a photograph of current construction.