A railroad truss over Red Oak Creek in Red Oak, photographed May 8, 2013, by Patrick Feller. This is a file photograph of the creek and bridge, not of City Hall, the Compass campus, or the Nov. 17 council meeting. Cropped and resized. (Patrick Feller, CC BY 2.0, Wikimedia Commons. Cropped and resized.)

Sidney Sherman

November 19, 2026 · 3 min read

Red Oak Council Votes 4-1 to Expand Compass Data Center Zoning

On Nov. 17, Red Oak City Council voted 4-1 to rezone about 886.5 acres for a Compass data center campus, FOX 4 reported.

Red Oak's City Council voted 4-1 on Tuesday, Nov. 17, to approve a zoning change that would expand a Compass data center campus, FOX 4 reported. The council met jointly with the Planning and Zoning Commission at 7 p.m. in the Council Chamber at 101 S. Live Oak Street, according to the official agenda.

The city's website lists that address, with the mailing address P.O. Box 393, as being in ZIP code 75154. The agenda identifies the meeting site as the Red Oak Government Center. Official minutes of the joint meeting have not been posted. FOX 4 attributed the 4-1 tally to the City Council and did not list how each member voted. The station also did not report a separate tally for the Planning and Zoning Commission, which the agenda had scheduled to make a recommendation before the council considered the ordinance.

Item 3 on the agenda called for the council, after considering that recommendation, to adopt Ordinance No. 26-038, changing the zoning from Planned Development 191 and Agricultural District to Planned Development 194. The request, case ZC26-17, was filed by William Dahlstrom and covers about 886.5 acres, according to the agenda. FOX 4 described the expanded property as nearly 900 acres. Dock Line is using the 886.5-acre figure printed on the city's agenda.

The agenda says PD-194 would allow a data center campus, with a concept plan and a development plan, plus rules on landscaping, lighting, sound, building elevations and a public park. The tracts are identified by Ellis County Appraisal District property numbers 190052, 191657, 290627, 259985, 181631, 290531, 181627, 181625 and 187997.

A Compass project page linked from the agenda, last updated Nov. 2, places the campus at 367 Oglesby Road. The company describes a 10-building campus and says it would leave more than half the land undeveloped, with 100 acres set aside as a public park and trails along Brushy Creek. That same page is not consistent on the size of the site. In one section it calls the land an 867-acre site; in another it refers to a 900.5-acre site. Those are the company's figures, and they do not match the city's 886.5-acre rezoning description.

FOX 4 reported that the meeting opened with an executive session lasting 30 minutes, then a packed public-comment period with standing room only. People who supported the project wore red shirts and declined to speak on camera, the station said. Residents who opposed the expansion lined up to talk.

FOX 4 quoted one opponent at length: "We hear you say over and over that everybody wants more things, more parks and better roads. And you say data centers give you the money to do that without raising taxes. But none of you has ever asked the people directly if we wanted to trade our peace and tranquility for those things." The same resident continued: "From six months of watching these meetings, I've learned that your decisions never consider the humans you're supposed to serve."

A supporter, also quoted by the station, said: "They're already approved. They already have their one campus done. And I feel really good about what they're doing in the community."

FOX 4 reported that the city had already approved zoning for more than 800 acres, and that the earlier decision is being challenged in court. The station did not describe the claims in that lawsuit, and the agenda did not add detail. Dock Line is not treating the new ordinance as a ruling on that case.

Elsewhere in Texas this week, Cameron County commissioners voted 3-2 against setting a hearing on a tax break SpaceX sought for a planned data center and power plant in Starbase. That vote was about a tax-abatement hearing, not a rezoning, and it does not decide what happens next in Red Oak.