A fenced electrical substation and transmission towers under a cloudy sky at the Gable Street substation in Houston, photographed in December 2022
The Gable Street substation in Houston, photographed in December 2022. File photo; neither bill names this site. Senate Bill 338 would attach cooling and water-reporting conditions to certain ERCOT interconnections for large data-center sites. (HighVoltage 5576 / Wikimedia Commons)

Jane Long

November 16, 2026 · 5 min read

Bills Would Condition New Data-Center Tax Deals or End Sales-Tax Exemptions

Sen. Charles Perry's SB 338, filed Nov. 12 with 15 other Senate authors, would attach cooling and water conditions to new data-center tax agreements and certain ERCOT hookups. Rep. Jessica González's HB 1139, filed Nov. 13, would repeal sales-and-use-tax exemptions and end those already in place on the effective date.

Two pre-filed bills for the 2027 session would take different paths on Texas data-center tax breaks. Senate Bill 338, filed Nov. 12 by Sen. Charles Perry of District 28 and 15 other senators listed as authors, would attach cooling, water-reporting, and other conditions to new property-tax limitation and abatement agreements and to certain ERCOT grid connections. A day later, on Nov. 13, Rep. Jessica González of Dallas filed House Bill 1139. That bill would repeal sales-and-use-tax exemptions for certified qualifying data centers and large data-center projects and would end exemptions already in place on the act's effective date. The two measures are not companions. Both are filings, not law.

Dock Line reported on the first filing day that House Bill 408 by Rep. Carrie Isaac and House Bill 167 by Rep. Trey Martinez Fischer would also repeal those sales-tax exemption statutes. The filed text of HB 408 would let a project already certified keep its exemption until its period expires, and would treat a pending certification application as denied. González's later filing is not a companion to those bills. Its Section 5 is stricter on existing deals: an exemption under Tax Code Section 151.359 or 151.3595 "to which a qualifying data center or qualifying large data center project is entitled on the effective date of this Act expires on that date." A pending application "is considered to be denied and may not be approved by the comptroller." The filings also come as Governor-elect Gina Hinojosa has promised to freeze new data-center approvals until lawmakers act. This story is about the Nov. 12 and Nov. 13 tax and water filings, not that earlier promise or those Nov. 9 repeal bills.

Senate Bill 338 would take effect Sept. 1, 2027. Its tax and incentive changes would apply only to agreements, loans, or grants entered into on or after that date. Public Utility Commission of Texas rules under a new data-center-customer section of the Utilities Code could apply only to a site interconnected to the ERCOT grid on or after that date, and a new Texas Commission on Environmental Quality requirement only to applications filed on or after that date.

For its Tax Code abatement chapter, the Senate bill would define a "data center" as a site with one or more facilities that "individually or collectively are at least 100,000 square feet in area" and "are constructed or adapted to house servers and related equipment and support staff for the processing, storage, and distribution of data."

For school-district maintenance-and-operations taxes, the bill would amend Government Code Section 403.605(a), which sets the taxable value of eligible property under a Subchapter T agreement. The amended text would make that value equal to 50 percent of market value; or, "if the property is used as part of an eligible project that is a data center, not more than 50 percent of the market value"; or, if the property is in a qualified opportunity zone, 25 percent of market value. The text does not say what share below 50 percent a data-center agreement would have to use.

New Section 403.6121 would add terms when the eligible project is a data center. The applicant would have to cool the data center, including any generation resource at the site, with only a closed-cycle recirculating, dry, saline-water, or water-efficient cooling system, or a combination of those systems, as defined in new Utilities Code Section 39.920. When the agreement is executed, the applicant would have to give the PUC an estimate of annual cooling-water needs and sources, then report actual use and sources yearly after construction is completed while the center operates. The applicant would have to own the data center for the term of the agreement, pay to remediate environmental harm from its construction, operation, presence, abandonment, or demolition, and, with a stated exception, convey to the school district a recorded nonpossessory interest permanently limiting the site to those cooling systems. The applicant would also have to comply with any PUC standards under Section 39.920 "limiting light and noise pollution" or "regulating the minimum distance of any component building of the data center to the boundary of the data center." The governor or the school district could terminate the agreement for failure to comply with "any term," after written notice and a 180-day period "to cure and dispute the alleged failure, including through judicial action." Termination would trigger a state penalty "equal to all lost ad valorem tax revenue from the project and interest on that amount," calculated under Tax Code Section 111.060.

A municipality could not abate "more than 50 percent of the portion of the value of the property that is otherwise subject to abatement" in any year of a Chapter 312 data-center agreement. New Section 312.2042 would attach similar cooling, water-reporting, ownership or lease, and remediation conditions, and a like penalty if the city terminated the deal. Chapter 380 municipal loans or grants for constructing or operating a data center could not be made unless the city or a development corporation entered an agreement meeting the applicable Section 312.2042 requirements. County and other taxing-unit agreements would follow those same terms.

The PUC would have to require certain large-load customers at a 100,000-square-foot-or-larger data-center site interconnected, or seeking interconnection, to the ERCOT grid to register the facilities, use only the listed cooling systems before interconnecting, and file water estimates and annual reports, which the commission would share at least yearly with the Texas Water Development Board. The commission would have to bar an electric cooperative, municipally owned utility, or transmission and distribution utility from interconnecting a site that lacked the required cooling system or paperwork, and require a disconnect if the customer later used a different cooling system or missed the annual report. An applicant for authority to discharge from a data center under a general permit for construction stormwater would have to attest to the Texas Commission on Environmental Quality that the project is or will be in compliance with applicable PUC standards. After a hearing, the commission would have to deny or suspend that authority if it found noncompliance, and issue an emergency order stopping construction if it reached that conclusion from a complaint or "other means."

House Bill 1139 would strike the Tax Code Section 151.317 exemption for gas and electricity used directly by a comptroller-certified qualifying data center under Section 151.359, or qualifying large data-center project under Section 151.3595, in the processing, storage, and distribution of data. It would repeal Sections 151.359, 151.3595, and 313.009 and clean related municipal and county sales-tax cross-references. The official statutes site was not used. It would take effect immediately if it received a two-thirds vote of all members elected to each house, as provided by Article III, Section 39, of the Texas Constitution; otherwise Sept. 1, 2027. Neither SB 338 nor HB 1139 sets a dollar figure or counts certified data centers.