The United States Post Office in Lavon, photographed Nov. 7, 2015. The Nov. 17 council meeting was held at City Hall, 120 School Road, not at this building. No sufficiently large public-use photograph of Lavon City Hall was found. (Michael Barera, CC BY-SA 4.0, Wikimedia Commons. Cropped and resized.)

Sidney Sherman

November 23, 2026 · 3 min read

Lavon Adopts 90-Day Moratorium on Data Center Development

Lavon council last Tuesday, Nov. 17, adopted a 90-day pause on data-center filings inside the city, according to the signed ordinance posted by the city.

The Lavon City Council last Tuesday, Nov. 17, adopted a 90-day moratorium on new data-center filings inside the city limits. The signed Ordinance No. 2026-11-03, posted with the city's official codes, records that the council approved the measure on first reading Oct. 20 and on second reading Nov. 17, and that it took effect immediately. The second and final reading appeared as item 8.B on the consent agenda for a regular meeting that began at 6:30 p.m. at City Hall, 120 School Road.

Mayor Vicki Sanson signed the ordinance, and City Secretary Rae Norton attested it, with the city seal. Official minutes of the Nov. 17 session had not been posted with the records reviewed for this report, so this article does not assign a roll-call tally to the second reading. A staff brief in the official Nov. 17 agenda packet quotes state law as requiring a final-reading supermajority equal to three-fourths of the full council before such a commercial-development pause can take effect.

The ordinance pauses the filing, review, and approval of development paperwork—including permits, plats, zoning changes, site plans, occupancy certificates, and related verifications—when a project would use a data center as its main use or as an accessory use. It applies only inside Lavon's corporate limits. A data center is defined there as a dedicated building that houses networked servers, data-storage systems, and telecommunications equipment used to store, process, and manage large amounts of digital information. The pause is meant to give the Planning and Zoning Commission and the council time to examine the city’s comprehensive plan, zoning rules, and other ordinances and to consider changes. The ordinance expires 90 days after adoption unless it is extended as allowed by law. An applicant may seek a waiver in writing; the council is to vote on that request within 21 days, or within 10 days if the request is made under Section 212.137 of the Texas Local Government Code.

In written findings, the council states that the city is not now planning or reviewing a particular data-center project, and that such facilities can raise issues of heavy power use, large water demand, and noise. It finds that existing city rules may not be enough to address those effects and that a temporary pause is needed while updated controls are studied. The ordinance cites the commercial-moratorium provisions of Texas Local Government Code Chapter 212, including the requirement for written findings when a commercial pause is not tied to a lack of essential public facilities.

Staff materials in the same official packet, including a Nov. 9 presentation prepared for the second reading, state that Lavon has no operating data centers, has received no plat, site-plan, or building-permit filings for such a use, and has not offered or approved economic-development or tax incentives, or entered nondisclosure agreements, for a data-center project. The presentation says the pause would cover the entire city, estimated at 5.26 square miles, and that planned-development zoning from 2013, 2019, and 2022 allows data-center uses in some districts, which it describes as the only areas zoned for that use or for business-park-type uses.

The official minutes of the Oct. 20 meeting show the first reading was approved unanimously, on a motion by Council member Mike Cook, Place 2, seconded by Mayor Pro Tem Mike Shepard, Place 1. Mayor Sanson and council members Travis Jacob, Rachel Dumas, and Lindsey Hedge were also present. A second public hearing that night opened at 6:56 p.m. and closed at 7:28 p.m. Several Lavon and county residents spoke in favor of a pause, and one resident offered a proposal of safeguards, the minutes say. City Manager Kim Dobbs told the council that no data-center applications had been received and that the city had not offered or approved related tax breaks or economic-development incentives. The packet brief traces the work to an Aug. 6 council presentation and direction and to a first public hearing on Sept. 15.

The city's contact page lists City Hall at 120 School Road, Lavon, Texas 75166. The U.S. Census Bureau's address geocoder returns the same match and places the building in Lavon, in Collin County. Dock Line has also reported on other Texas cities writing local data-center rules, including Taylor's work on setbacks and noise limits.