Magnolia ISD Names Kresston Elementary, OKs $5.89 Million Package
Magnolia ISD named its next elementary school Kresston Elementary and approved a $5,885,240.42 first work package on Nov. 16, Community Impact reported.
MAGNOLIA, Texas — Magnolia ISD trustees on Monday named the district's planned Elementary School No. 10 as Kresston Elementary and approved a $5,885,240.42 first construction package for the campus, Cole Gee of Community Impact reported after the Nov. 16 regular meeting.
Both actions were listed on the posted agenda as considered items 9.A and 9.B. The agenda set the meeting for 6:30 p.m. and asked the board to approve a name for the future elementary site in the Kresston development and to approve pricing for Elementary School No. 10. Neither the agenda nor the Community Impact report published a name-by-name roll call, and this article does not invent one.
A board item from Superintendent Dr. Jason Bullock recommended the name Kresston Elementary School. It says the district bought the property in the Kresston development, off FM 1486, for the new campus, and that the site is meant to ease rising enrollment at Audubon Elementary and possibly at Williams Elementary. The item says the name follows board policy and reflects the board's intent, worked out with Johnson Development.
The $5,885,240.42 figure comes from a board item on Package 1, which identifies B&C Constructors as the construction manager at risk for the school under the 2026 bond program. The item says the company took subcontractor bids on Oct. 29 after advertising the work, and that this early-release price is meant to be folded into the school's later guaranteed maximum price. It describes Package 1 as clearing and grubbing, a building pad and grading, underground electrical work, and a structural steel package.
The accompanying Oct. 30 proposal from B&C Constructors, L.P., addressed to facilities director Tim Bruner, breaks the same official total into these lines: temporary facilities, $10,000; temporary fencing, $20,000; a stormwater pollution prevention plan, $28,000; underground electrical work, $232,707; clearing, grubbing, the building pad and grading, $835,000; and a structural steel package, $4,405,534. Subcontractor direct costs are listed at $5,531,241. General conditions of 4.55 percent are listed at $251,671.47, and a contractor's fee of 1.85 percent is listed at $102,327.96. The proposal's total is $5,885,240.42.
Steel is the largest line in the package. Bruner, the district's executive director of facilities, told Community Impact that recent inflation had pushed the steel cost up an estimated 36% to 37%, or about $1 million, from a steel package the district bought in 2023. Those figures are his estimates, as reported by the news outlet, not totals from the bid documents.
Package 1 is only the first slice of the school's budget. The district's Bond 2026 materials list Elementary School No. 10 at $53,974,760, place it in the Kresston development, and give an August 2028 opening. That campus is part of the $465,688,326 single-proposition bond voters approved in May. This article treats the August 2028 date as the plan now on the district's bond page, not as a finished timetable. The Package 1 item does not set a construction start date, and none is supplied here.
The BoardBook public listing for the Nov. 16 regular meeting gives the location as the Magnolia ISD Event Center, 11659 FM 1488, Magnolia, TX 77354. The U.S. Census Bureau's official address geocoder, queried for that street address, returns ZIP code 77354. Related: Growth Isn't Moving in One Direction. It's Moving in Several at Once. Also: Part 2: The Houses Are Coming. Who Pays for the Roads, Water and Drainage?.